The Perils of Not Going "Genchi, Gembutsu" (On Site, With the Actual Things)

I take a lot of people from many companies to Japan to see lean organizations, such as the Toyota Motor Corporation. One of the themes you see and hear in Toyota is the idea of Genchi (actual place) and Gembutsu (actual things). Toyota wants decisions that relate to a certain area made right at that area. One example is a plan to prevent downtime on a machine should be made right by that machine.

Let me show you one reason Genchi Gembutsu is so important. One company I know has their managers flooded with reporting. Decisions about sites are not made on site and therefore require a lot more reporting, planning and detail than would be otherwise necessary.

Let me give you an example. You're a manager of a site and you are supposed to give a report about how everything is going to your Vice President, who is back at headquarters which is off site from the plant. The plant is a dynamic organization and trying to put all aspects of the plant on 3 pieces of 2 dimensional paper is not going to tell the whole story.

Your VP obviously is expected to comment on the report. If she just said "hmmmm, looks good, thanks a lot!" most people would think she's not doing her job, right? So she will ask questions.

The 2 dimensional report cannot show the whole picture. The VP will be asking questions away from the site, so the starting point of her understanding is uncertain to begin with. The value system of corporate America is: Even though you don't understand it completely, ask questions anyway.

You, as the manager, have some options.
a) You can tell the VP, "I don't know," and look incompetent.
b) You can say, "I really can't explain it properly to you here," and appear belligerent, or worse, insinuate that your boss is incompetent.
c) Prepare more reports for anticipated questions. Hopefully the appearance that everything is under control will satisfy your VP.

The best choice is clearly to do more reports. The initial report took one person 4 hours to prepare and you 2 hours to finalize. Now, more reports are needed, which will take another person 8 additional hours to prepare and you another 1-2 hours, not to mention all the other paperwork that goes along with it. It's a vicious cycle.
1. The report won't tell the whole picture.
2. People will ask questions based on an unclear picture of what's happening and on the report that doesn't tell the whole picture.
3. You spend time preparing more reports to back up what the initial report says.
4. You have less time to run the company and start fixing problems.
5. You get a laundry list that you need to complete by the next report which will necessitate more paperwork and more reports
6. Return to #1.

Recently I talked to a manager who said he prepared 5 hours for a monthly report which took 8 hours which he had to give twice! Imagine how many hours the people underneath him prepared. When I asked who the report was for, they told me that person who was in charge of production had not been in the plant for 10 months! Ouch!

He then spent another 4 hours in front of me on a conference call going over action items that would get them back on track on their action plan (It was close to a 500-item action plan) to someone who had not stepped in the doors of the facility in person in almost a year!

The tragedy about this is the amount of muda, or waste, is horrendous because it is wasting the best and brightest minds of the company. If nothing else, it's wasting the most expensive minds of the company.

To those of us who are managers and owners of companies, let's try to make decisions at the Genchi (on site) and with the Gembutsu (actual things). I think we will all be surprised to see how much waste our previous reporting / meetings had in them and how much we can eliminate by trying to emulate Toyota's philosophy of decision making.

By Jon Miller - November 21, 2005 3:11 PM

Comments

Post a Comment

Comments are moderated to filter spam and inappropriate content. There may be a delay before your comment is published.




Recent Artices
Virtual Facory Tours on YouTube

Keep your chin up, global manufacturing! Even though new factory orders dipped recently to record more>>

By Jon Miller - January 4, 2009 4:53 PM0 comments>>
Ask Gemba

We want to make it easier to start conversations and find answers here at more>>

By Jon Miller - January 3, 2009 1:57 PM0 comments>>
5 Ways to Boost Kaizen Consciousness in 2009

Improved quality, reduced cost, better teamwork, faster response to customer needs - there are as more>>

By Jon Miller - January 1, 2009 11:19 PM1 comments>>
HP Printer Pokayoke Example

This is a new HP C7250 printer we purchased a few weeks ago. It's quite more>>

By Jon Miller - December 30, 2008 12:53 AM0 comments>>
Yaruki: The Will to Win Even in Tough Times

RC Bhargava, the Chairman, Maruti Suzuki India recounts the story of Maruti Suzuki and how more>>

By Jon Miller - December 28, 2008 7:53 PM3 comments>>
9 Surprises for U.S. Manufacturing in 2009

1. Will you shut up about kaizen, Tom? Newly appointed U.S. Secretary of Agriculture more>>

By Jon Miller - December 24, 2008 4:05 PM4 comments>>
Let's Do Kaizen, Not Kaizan

It doesn't really matter how you pronounce the Japanese word for continuous improvement through more>>

By Jon Miller - December 23, 2008 12:20 PM0 comments>>
Answers to Lean Thinking Crossword Puzzle #1

Spoiler alert! The answers to Lean Thinking Crossword Puzzle #1 are below. Here are the more>>

By Jon Miller - December 20, 2008 2:20 AM0 comments>>
Lean Thinking Crossword Puzzle #1

Here is a quiz we used as a review of lean knowledge for the team more>>

By Jon Miller - December 19, 2008 3:24 AM0 comments>>
Field Report from Gemba Tour #62, Part 4

Today was day-long visit to a company who is 13 years on their lean more>>

By Jon Miller - December 18, 2008 8:16 AM1 comments>>
Field Report from Gemba Tour #62, Part 3

Today wast the Toyota plant tour day of our Japan Kaikaku Experience #62. I noticed more>>

By Jon Miller - December 17, 2008 5:21 AM0 comments>>
Field Report from Gemba Tour #62, Part 2

I have seen the future of logistics, and it is green. Today we visited more>>

By Jon Miller - December 16, 2008 7:08 AM3 comments>>
Field Report from Gemba Tour #62, Part 1

The last few weeks haven't been very productive ones for writing blog articles due more>>

By Jon Miller - December 15, 2008 5:34 AM2 comments>>
If Blame Helped Solve Problems...

...the interview with Newt Gingrich on Fox News would be a brilliant way to get more>>

By Jon Miller - December 5, 2008 11:07 PM8 comments>>
$34,000,000,000

Sigh. Chrysler wants $7 billion. They asked Congress for this taxpayer money in a 14-page more>>

By Jon Miller - December 2, 2008 8:11 PM5 comments>>
PDCA is About Not Telling Lies

This circle doesn't lie. In fact one could say that used properly, it is more>>

By Jon Miller - December 1, 2008 5:39 AM6 comments>>
With Competitors Like These, Who Needs a Winning Business Strategy?

Larry, Curly and Moe go to Washington image credit: Wall Street Journal As we more>>

By Jon Miller - November 27, 2008 10:00 PM4 comments>>
It's a Lousy Time to Implement Lean

Author, teacher and our friend Bob Emiliani from the Center for Lean Business Management pointed more>>

By Jon Miller - November 25, 2008 8:08 PM4 comments>>
The Big 3 Must Follow in Toyota's Footsteps to Survive

The Big 3 automotive companies must follow in Toyota's footsteps to survive. There are three more>>

By Jon Miller - November 23, 2008 7:34 PM6 comments>>
Ambiguous Visual Controls: This Way is Up

This makes it three for three on scoring photos of ambiguous visual controls during visits more>>

By Jon Miller - November 12, 2008 2:51 PM3 comments>>
Blogroll
Improve With me
Lean Companies
Agile Management Blog
Curious Cat
DailyKaizen
Evolving Excellence
Fashion-Incubator
Got Boondoggle?
Lean Blog
Lean Insider
Lean Builder
Lean Reflections
Lean Six Sigma Academy
Learn Sigma
Productivity Cafe
Reforming Project Management
Shmula
The Lean Thinker
Thinking for a Change
TPM Log