One of the main drivers of non-lean behavior such as local optimization, batch work, and building up inventory is the desire to avoid time lost during changeovers between one job to another type of job. Sometimes this is reinforced by how we make financial measurements, seeking to earn hours or absorb cost (both of which ought to be in quotes) by utilizing the asset to the maximum. If we delve into the reasons why we would see more than one root cause for this behavior that builds up barriers between processes and people, lengthens cycle time to the customer, and drives overproduction: the mother of all wastes.

The changeover analysis sheet used in combination with a pencil, astopwatch and two feet planted firmly within an Ohno circle is usually good to chop 50% to 80% of the time off of a changeover process that has not been kaizened in the past. Often repeated reductions of 50% are possible all of the way down to single digit changeovers, the aim of Single Minute Exchange of Dies (SMED). There is always a smaller unit of measure, after all.

changeover%20analysis.png

When working on changeover reduction, the main thing you need to know is the difference between internal time and external time. Internal set up time or internal changeover time (same thing) is time spent on the changeover with the machine or process stopped. This work is "internal" to the down time. External set up or external changeover time is the changeover time for work done while the machine or process is still running. This work is "external" to the downtime. The goal of course is to minimize the downtime so the less internal time you have the better.

As in this example of changeover analysis, many unexamined changeovers are purely internal changeover work. The machine stops, and then the worker goes to look for the work order, the materials, the tools, the inspector to sign off on the first piece, etc. It's a simple matter of categorization, planing and coordination to externalize much of set up work.


changeover%20analysis%20example.png

Using a video camera with a timer can give changeover analysis a powerful boost. In addition to being able to pause the video, observe the process repeatedly, and check the times against a running clock, you can spend less time worrying about writing down task times and more times observing the work and asking "why?" during the live changeover. If a video camera is not available, do this changeover kaizen as a team effort with 2 to 4 people, each assigned a specific task such as calling out times on the running clock, writing down comments and observations, or drawing the lines of movement on a spaghetti diagram - next week's template.

Whether video taping, timing or asking questions about the changeover process, always practice respect for the people being watched, timed and taped. For most people it is really not comfortable to have a team silently scribbling away with stop watches, or worse, sighing and shaking their heads at all of the waste they see. Involve, educate and empower the team member and they will reward you with many great ideas on how to kaizen changeover time.

By Jon Miller - February 7, 2008 8:15 PM

Comments

Post a Comment

Comments are moderated to filter spam and inappropriate content. There may be a delay before your comment is published.




Recent Artices
Virtual Facory Tours on YouTube

Keep your chin up, global manufacturing! Even though new factory orders dipped recently to record more>>

By Jon Miller - January 4, 2009 4:53 PM0 comments>>
Ask Gemba

We want to make it easier to start conversations and find answers here at more>>

By Jon Miller - January 3, 2009 1:57 PM0 comments>>
5 Ways to Boost Kaizen Consciousness in 2009

Improved quality, reduced cost, better teamwork, faster response to customer needs - there are as more>>

By Jon Miller - January 1, 2009 11:19 PM1 comments>>
HP Printer Pokayoke Example

This is a new HP C7250 printer we purchased a few weeks ago. It's quite more>>

By Jon Miller - December 30, 2008 12:53 AM0 comments>>
Yaruki: The Will to Win Even in Tough Times

RC Bhargava, the Chairman, Maruti Suzuki India recounts the story of Maruti Suzuki and how more>>

By Jon Miller - December 28, 2008 7:53 PM3 comments>>
9 Surprises for U.S. Manufacturing in 2009

1. Will you shut up about kaizen, Tom? Newly appointed U.S. Secretary of Agriculture more>>

By Jon Miller - December 24, 2008 4:05 PM4 comments>>
Let's Do Kaizen, Not Kaizan

It doesn't really matter how you pronounce the Japanese word for continuous improvement through more>>

By Jon Miller - December 23, 2008 12:20 PM0 comments>>
Answers to Lean Thinking Crossword Puzzle #1

Spoiler alert! The answers to Lean Thinking Crossword Puzzle #1 are below. Here are the more>>

By Jon Miller - December 20, 2008 2:20 AM0 comments>>
Lean Thinking Crossword Puzzle #1

Here is a quiz we used as a review of lean knowledge for the team more>>

By Jon Miller - December 19, 2008 3:24 AM0 comments>>
Field Report from Gemba Tour #62, Part 4

Today was day-long visit to a company who is 13 years on their lean more>>

By Jon Miller - December 18, 2008 8:16 AM1 comments>>
Field Report from Gemba Tour #62, Part 3

Today wast the Toyota plant tour day of our Japan Kaikaku Experience #62. I noticed more>>

By Jon Miller - December 17, 2008 5:21 AM0 comments>>
Field Report from Gemba Tour #62, Part 2

I have seen the future of logistics, and it is green. Today we visited more>>

By Jon Miller - December 16, 2008 7:08 AM3 comments>>
Field Report from Gemba Tour #62, Part 1

The last few weeks haven't been very productive ones for writing blog articles due more>>

By Jon Miller - December 15, 2008 5:34 AM2 comments>>
If Blame Helped Solve Problems...

...the interview with Newt Gingrich on Fox News would be a brilliant way to get more>>

By Jon Miller - December 5, 2008 11:07 PM8 comments>>
$34,000,000,000

Sigh. Chrysler wants $7 billion. They asked Congress for this taxpayer money in a 14-page more>>

By Jon Miller - December 2, 2008 8:11 PM5 comments>>
PDCA is About Not Telling Lies

This circle doesn't lie. In fact one could say that used properly, it is more>>

By Jon Miller - December 1, 2008 5:39 AM6 comments>>
With Competitors Like These, Who Needs a Winning Business Strategy?

Larry, Curly and Moe go to Washington image credit: Wall Street Journal As we more>>

By Jon Miller - November 27, 2008 10:00 PM4 comments>>
It's a Lousy Time to Implement Lean

Author, teacher and our friend Bob Emiliani from the Center for Lean Business Management pointed more>>

By Jon Miller - November 25, 2008 8:08 PM4 comments>>
The Big 3 Must Follow in Toyota's Footsteps to Survive

The Big 3 automotive companies must follow in Toyota's footsteps to survive. There are three more>>

By Jon Miller - November 23, 2008 7:34 PM6 comments>>
Ambiguous Visual Controls: This Way is Up

This makes it three for three on scoring photos of ambiguous visual controls during visits more>>

By Jon Miller - November 12, 2008 2:51 PM3 comments>>
Blogroll
Improve With me
Lean Companies
Agile Management Blog
Curious Cat
DailyKaizen
Evolving Excellence
Fashion-Incubator
Got Boondoggle?
Lean Blog
Lean Insider
Lean Builder
Lean Reflections
Lean Six Sigma Academy
Learn Sigma
Productivity Cafe
Reforming Project Management
Shmula
The Lean Thinker
Thinking for a Change
TPM Log